A Major Central
States Railroad
A major central
states railroad experienced a diesel spill at a fuel depot due to a
large rain storm flooding a catch basin overflowing the basin’s residual
fuel into a waterway. As an OSRO certified contractor maintaining the
proper qualifications, trained staff and equipment to manage spills on
water, HMRI responded to the incident location to provide emergency and
site remediation assistance. Action plan objectives included deployment
of hard boom to create collection points, placement of soft absorbents
at the connection points to minimize possible migration beyond
collection points, utilization of floating pumps to push product to the
catch points, removal of the fuel from the waterway with the use of a
vacuum truck and removal of surface contamination along the banks.
After the initial event, Haz-Mat Response provided weekly site
evaluations and site maintenance.
Throughout the incident, the client was
kept informed of actions taken at the site. A final report, including
photos of the site, was provided to the client for their official record.
Water Recovery and Clarification
An industrial
manufacturing plant in Kansas City, MO, required assistance with recovery of
approximately 70,000 gallons of oil contaminated water resulting from fire
suppression operations at their facility. Haz-Mat Response recovered the
oil contaminated water into large storage tanks with the use of vacuum
trucks and pumps. Site cleaning operations included pressure washing a
large concrete pad, with recovery of resultant contaminated water added to
the previously recovered fire suppression water.
Since the
customer’s wastewater treatment facility could not handle processing the
added volume of water, Haz-Mat Response filtered the recovered water using
bag filters and a one ton carbon vessel, thus, allowing the filtered water
to be released to the treatment plant on a scheduled basis.
Debris
from the fire and storage tanks clean out were solidified by Haz-Mat
Response crews. The debris and drums containing the carbon media used to
scrub the water were placed into roll-off containers which were then
transported to the customer’s designated landfill.
After an initial orientation of the plant,
Haz-Mat Response crews were allowed to operate with indirect supervision.
Operational objectives and coordination of the project were left to the
Haz-Mat Response’s Project Manager.
Butane Tanker
Rollover
Haz-Mat Response crews were asked to respond to the scene of a rollover
accident in Wichita involving a pressurized tanker containing butane. Upon
arrival at the scene and after meeting with local emergency responders for
accurate, current site situation, the crew assessed the tanker’s damage
finding a small leak in the liquid line and structural damage to the tanker.
The technicians exited the hot zone to update the local emergency response
agencies. The Haz-Mat Response crew provided assistance in the development
of an action plan to unload the tanker, control access to the site and
remediate the site.
Haz-Mat
Response’s action plan tasks and objectives included:
Once the
transfer began, Haz-Mat responders remained on stand by in the tanker’s hot
zone to insure its successful completion. The transfer operation took
slightly more than two hours, with successful transfer of 98 percent of the
butane. After the transfer, Haz-Mat Response removed their equipment from
the site, but remained on standby while the damaged tanker was loaded onto a
flatbed trailer for transport back to the shipper’s maintenance yard. The
remaining remediation tasks were completed before the crew left the scene.
Paint spill inside
of a tractor trailer
A Haz-Mat Response crew was called to an accident site involving a tractor
trailer transporting a load of paint, which is considered to be a flammable
liquid. The tractor trailer had run off of the interstate, overturning onto
its side on a side road.
Upon arrival on site, the Project Manager
conducted a site assessment, determining that the 465 five-gallon buckets of
paint were not salvageable, that the tractor trailer’s top was destroyed by
the paint cans catapulting through the truck as it rolled, and that
approximately 1/8 of a mile from the interstate across a side road into a
nearby field was impacted with paint.
Haz-Mat Response technicians removed the
contamination using dirt moving equipment and four roll-off boxes, enabling
the side road to be reopened within 3½ hours. Haz-Mat Response arranged for
free roll-off box storage with a near by landowner until proper disposal
could be authorized, thus assisting the trucking company to contain costs.
Upon receipt of disposal authorization, Haz-Mat Response crews hauled the
boxes to a landfill and completed remediation of the site.
Haz-Mat Response’s crew, consisting of a
Project Manager, an equipment operator, a truck driver and a laborer,
restored the site within 24 hours of the accident.
Gasoline tanker
rollover
Haz-Mat Response’s
crew responded to an accident involving a tanker carrying 8,500 gallons of
unleaded gasoline. During the accident, the tractor and trailer become
separated. The tractor, after traveling through a ditch coming to rest on
its right side on a gravel side road, is destroyed by fire. Although the
tanker never caught fire, it sustained heavy damage, including a leak in its
vent recovery system.
Upon
arrival at the scene, the Haz-Mat Response team met with the local emergency
response team. While local responders provided air monitoring and charged
fire hose lines as safety measures, the Haz-Mat response team entered the
trailer’s hot zone to assess its damage and evaluate transfer options.
After exiting the site, the crew met with local responders, outlining the
need for safety measures and a transfer plan.
A tow
truck was used to secure the tanker during the transfer. The site was bonded
and grounded allowing Haz-Mat Response technicians to safely hot tap the
tanker and transfer its fuel into a second tanker.
After the
transfer was complete and the tanker removed, crews excavated the site,
stockpiling the contaminated soil. Bottom samples were taken to insure the
site was clean. Haz-Mat Response coordinated disposal of the contaminated
soil and backfilling of the site.
Soda ash derailment
A railroad official requested use of Haz-Mat Response’s Guzzler vacuum truck
to clean up soda ash from a derailment. Upon arrival at the site, the
Haz-Mat Response crew found two railcars of soda ash on their side in the
railyard’s retarders. The railroad requested that the retarders be vacuumed
first allowing signal and track crews to reopen the hump’s operations.
Once the hump was back in service, Haz-Mat
Response crews were asked to remove the remaining soda ash from the cars
without interrupting the hump’s operation. The crew used a Guzzler vacuum
truck and a roll-off vacuum box to remove the soda ash from the cars. The
cars were then righted and loaded onto flat cars for transport to repair
facility. The soda ash was loaded into roll-off boxes and transported to a
landfill for disposal.
Lube oil and sodium
hydroxide train derailment
Haz-Mat Response assisted with the response and clean-up following a
derailment involving leaking railcars of lube oil and sodium hydroxide. The
products had flowed into a small stream located within the railroad’s
right-of-way. Haz-Mat Response was assigned the responsibility of
containing the spill, recovering the product and excavating the site. Tasks
and objectives included:
Throughout
the incident, Haz-Mat Response provided the customer with a wide range of
equipment including pumps, vacuum trucks, heavy equipment, all-wheel drive
site transportation, pressure washers, containment boom, temporary storage,
absorbents, poly sheeting, site storage trailers and hand tools.
Throughout the four-month project, Haz-Mat
Response managed the site with indirect supervision, setting daily and
long-term objectives. The initial response required 24-hour operations
which were later scaled back to scheduled maintenance tasks.
Top of Page